ecozone editura ecozone iasi
Reviste:

» Environmental Engineering and Management Journal

» European Journal of Science and Theology

» Sănătate Sport și Nutriție


» Autentificare

E-mail:
Parola:
   
  Cont nou
Va rugam sa va autentificati pentru a putea comanda carti

» Cautare

  » Ultimele cautari

HYDROPOWER DEVELOPMENT OF BISTRIȚA RIVER UPSTREAM OF IZVORUL MUNTELUI LAKE
Autori: Costel Boariu
Data aparitiei: Iunie / 2016
Revista: Environmental Engineering and Management JournalVol. 15Nr. 6
ISSN: 1843 - 3707
Pret: 25.00 RON    
N.A.

This article refers to the fourth stage of the hydropower development of Bistrița River, upstream of the Izvorul Muntelui
impoundment, in the Borca-Poiana Teiului area. The original project (described in chapter 2) was altered during the execution of
works. The changes which have been made are significant: a decrease of the headrace area by 32% and the location of the power
plant has been changed. The magnitude of these changes might lead to the idea that either the original project or the current
changes are inappropriate. This article examines the impact of these changes on the final parameters of the hydropower
development and proposes solutions for the optimal completion of the works.. The energetic parameters of the developments
have been calculated using the analytical method (plotting the flow duration curve and calculating the energy produced as the
surface delimited by the flow duration curve, the servitude flow and the vertical axis) available when these works were designed
(in the ‘90s) and the RETscreen program, a modern instrument. The results obtained using the two methods have almost the same
values. The calculation methods are usual (known) but the result is surprising.



Sus

Acasa · Carti editate · Reviste · Despre editura · Abonament · Contact · Cos cumparaturi · Cum platesc? · Termeni si conditii
VisaMaster CardPayU

2001 - 2026 © Copyright Editura EcoZone Iasi Toate drepturile sunt rezervate.
Gazduire skaleweb.ro

SkaleWeb